05.06.2024 | Infraestrutura
This activity marks the beginning of the land works, which represents the preparation of the area for the container and general cargo yard. For this first phase, earthworks are being carried out, and in parallel the construction of rainwater drainage will be carried out.
In this first stage of the container yard, Imetame team involved in this activity has already advanced 11%, which represents 27,606.76m³ of cutting and filling.