Acompanhe

IMETAME PORT CONTAINER QUAY IS TAKING SHAPE

05.06.2024 | Infraestrutura


Warning: Array to string conversion in /home4/porto534/public_html/en/wp-content/themes/imetame/functions.php on line 59
Array

The driving of the piles for modules zero and 01 has already been completed. Now the focus is on completing module 02, which out of the 40 piles planned, 10 are already positioned.

In addition to the pile driving activities, another important action that is also contributing to the project’s long-awaited pier was started: assembly and concreting of the beams that make up the Imetame Logística Porto pier slab. This represents the beginning of the concreting of the first module of the Container Quay.

The activities of driving the piles and concreting the modules are expected to be completed by May/2025 for the partial operation phase with 400 meters of quay.