20.03.2024 | Infraestrutura
With its own equipment, Imetame Logística Porto continues to make progress in the construction of its enterprise. The “Backhoe” model dredger is in full operation and has already dredged more than 1.9 million cubic meters, with almost 60% of the first phase of dredging completed, reaching a depth of 12 meters in the first berthing area of the port.